The first three Pluto Train 2 modules for the Scarborough gas project have arrived in Karratha, Western Australia, Woodside Energy announced Feb. 21.
Bechtel fabricated the modules in Indonesia, with construction beginning in November 2021.
Together, the three modules weigh more than 4,000 metric tonnes. They are the first three of 51 modules that will be shipped to Karratha for Pluto Train 2, which is the second LNG production train at the existing onshore Pluto LNG facility.
Woodside is developing Scarborough in the Carnarvon Basin with a floating production semisubmersible moored in 950 m water depth near the gas field and eight initial wells. The Scarborough Field will be connected by a 430-km pipeline to Pluto Train 2.
The Scarborough project targets first LNG cargo in 2026 and is expected to reach production of 8 million tonnes per annum (mtpa).
Pluto Train 2 will process gas from the offshore Scarborough development and have an LNG processing capacity of approximately 5 mtpa. Pluto Train 1 will be modified to accommodate lean gas and process up to 3 mtpa from Scarborough.
“With the Scarborough energy project sitting at more than 55% complete, we are making significant progress across all scopes of work and look forward to receiving the remaining modules on site throughout 2024,” Woodside CEO Meg O’Neill said in a press release.
Recommended Reading
CEO: Continental Adds Midland Basin Acreage, Explores Woodford, Barnett
2024-04-11 - Continental Resources is adding leases in Midland and Ector counties, Texas, as the private E&P hunts for drilling locations to explore. Continental is also testing deeper Barnett and Woodford intervals across its Permian footprint, CEO Doug Lawler said in an exclusive interview.
Galp Seeks to Sell Stake in Namibia Oilfield After Discovery, Sources Say
2024-04-22 - Portuguese oil company Galp Energia has launched the sale of half of its stake in an exploration block offshore Namibia.
BP: Gimi FLNG Vessel Arrival Marks GTA Project Milestone
2024-02-15 - The BP-operated Greater Tortue Ahmeyim project on the Mauritania and Senegal maritime border is expected to produce 2.3 million tonnes per annum during it’s initial phase.
For Sale, Again: Oily Northern Midland’s HighPeak Energy
2024-03-08 - The E&P is looking to hitch a ride on heated, renewed Permian Basin M&A.
E&P Highlights: Feb. 26, 2024
2024-02-26 - Here’s a roundup of the latest E&P headlines, including interest in some projects changing hands and new contract awards.