Aker BP received a go-ahead to start-up production at its Hanz accumulation as a subsea tieback to the Ivar Aasen Field in the North Sea, the Norwegian Offshore Directorate (NOD) announced Feb. 27.
Hanz was proven in 1997 and is included in the 2013 plan for development and operation for the Ivar Aasen Field.
The project in 380 ft water depth is reusing the subsea installations on the Jette Field, which was shut down in 2016.
In a press release, NOD’s Tomas Mørch, assistant director of license management, called the use of existing infrastructure and an alternative method for pressure support a good use of resources.
Development costs for Hanz were about $400 million, and the project targets recovering about 20 MMboe.
Aker BP expects to begin production during the first quarter of 2024.
Aker BP operates PL028 B with 35% interest on behalf of partners Equinor with 50% and Sval Energi with 15%.
Recommended Reading
E&P Highlights: Feb. 16, 2024
2024-02-19 - From the mobile offshore production unit arriving at the Nong Yao Field offshore Thailand to approval for the Castorone vessel to resume operations, below is a compilation of the latest headlines in the E&P space.
BP: Gimi FLNG Vessel Arrival Marks GTA Project Milestone
2024-02-15 - The BP-operated Greater Tortue Ahmeyim project on the Mauritania and Senegal maritime border is expected to produce 2.3 million tonnes per annum during it’s initial phase.
TotalEnergies Fénix Platform Installed Offshore Argentina
2024-02-13 - First gas from the TotalEnergies-operated project is expected in fourth-quarter 2024.
E&P Highlights: Feb. 5, 2024
2024-02-05 - Here’s a roundup of the latest E&P headlines, including an update on Enauta’s Atlanta Phase 1 project.
E&P Highlights: March 4, 2024
2024-03-04 - Here’s a roundup of the latest E&P headlines, including a reserves update and new contract awards.