Marathon Petroleum Corp.’s Trans-Foreland Pipeline Co. unit received more time to convert the Kenai LNG export plant in Alaska into an import terminal, U.S. energy regulators said on Aug. 16.
The U.S. Federal Energy Regulatory Commission (FERC) approved Trans-Foreland’s request for an extension to complete the project until December 2025.
FERC first approved Trans-Foreland’s request to build the plant in December 2020 and gave the company until December 2022 to place it into service.
Trans-Foreland said it has yet to make a final investment decision (FID) to build the project because the COVID-19 pandemic and the war in Ukraine have worsened economic and logistical conditions.
“Uncertainty and volatility in the global LNG market have made it difficult for Trans-Foreland to secure a suitable supply arrangement that would provide the financial certainty necessary for the project,” Trans-Foreland said in an earlier filing.
Trans-Foreland, however, said the project “remains commercially viable.” The company said it “is actively seeking suitable supplies and monitoring LNG markets.”
Once Trans-Foreland makes commercial arrangements for suitable supply, the company said it anticipates making its FID and moving forward with the project.
Trans-Foreland has said the facility would import up to four tanker loads of LNG per year and use its boil-off gas management system to deliver imported gas to the adjacent Kenai refinery.
The Kenai LNG export plant entered service in 1969. It has not exported LNG since 2015.
The plant was the only big LNG export facility in North America until Cheniere Energy Inc.’s Sabine Pass export terminal in Louisiana entered service in February 2016. Nearly all of the LNG from Kenai went to Japan.
Recommended Reading
Exclusive: Adkins on Challenged Gas Prices, Growing Crude Demand
2024-05-15 - J. Marshall Adkins, head of energy investment banking at Raymond James, details the future of natural gas prices and misconceptions about crude demand coming to an end in this Hart Energy Exclusive interview.
CoolCo, GAIL Enter Long-term LNG Agreement
2024-05-16 - CoolCo and GAIL’s agreement is intended to secure long-term LNG supply in India’s market, with GAIL having an option to extend the 14-year agreement by another two years.
ConocoPhillips Looks to Scale Portfolio, But Citgo Auction Not a Factor
2024-05-15 - ConocoPhillips has a long-term ambition to boost its LNG offtake capacity to between 10 mtpa to 15 mtpa as it keeps a short-term eye on the auction of Citgo Petroleum.
Linde Doubles Production Capacity at Gulf Coast Facility
2024-05-14 - Linde’s expansion of the production capacity at its air separation facility in La Porte, Texas, will help meet growing demand for industrial gases in the area.
Gas Prices in a Summer of Discontent
2024-05-14 - In February, natural gas prices dropped below $2/MMBtu and stayed there. How is the market handling it, and when will the price pick back up?