Canadian regulator National Energy Board (NEB) on Feb. 15 issued rulings that allow Kinder Morgan Canada Inc. to do additional construction work on an oil pipeline expansion that is fiercely opposed by the province of British Columbia.
The board issued three decisions that collectively allow Kinder to start work in the Vancouver area on the Burnaby Mountain tunnel entrance of its Trans Mountain pipeline expansion, subject to other permits.
It lifted all remaining pre-construction conditions relating to the tunnel, and approved the pipeline’s route where the tunnel will be built.
The decisions inch the Trans Mountain expansion closer to reality; however Kinder Morgan Inc. (NYSE: KMI) reiterated that it was holding off on starting full construction while it awaited further permits and court decisions.
The NEB has approved just over half of the final route for the expansion, which is a twinning of an existing pipeline extending from Alberta’s energy heartland to a port in Burnaby, a suburb of Vancouver.
A lawyer for the city of Burnaby said that while rulings were expected, the speed of the decisions was frustrating, as detailed route hearings are still ongoing.
“It does seem that whatever Trans Mountain asks for, the NEB appears happy to provide,” said lawyer Greg McDade, adding the city will file an appeal on Feb. 16 over previous NEB rulings allowing Kinder Morgan to sidestep some municipal permits.
Kinder Morgan Canada noted the tunnel construction will not disrupt the surface of Burnaby Mountain, and avoids construction through residential neighborhoods.
The pipeline expansion is crucial for landlocked oil producers who receive deeply discounted prices from U.S. refineries because of transportation constraints.
British Columbia’s left-leaning government opposes the pipeline, and has threatened to block additional oil shipments through the province as it studies how to clean up potential spills.
Recommended Reading
Sinopec Brings West Sichuan Gas Field Onstream
2024-03-14 - The 100 Bcm sour gas onshore field, West Sichuan Gas Field, is expected to produce 2 Bcm per year.
Exclusive: Carbo Sees Strong Future Amid Changing Energy Landscape
2024-03-15 - As Carbo Ceramics celebrates its 45th anniversary as a solutions provider, Senior Vice President Max Nikolaev details the company's five year plan and how it is handling the changing energy landscape in this Hart Energy Exclusive.
E&P Highlights: April 8, 2024
2024-04-08 - Here’s a roundup of the latest E&P headlines, including new contract awards and a product launch.
ShearFRAC, Drill2Frac, Corva Collaborating on Fracs
2024-03-05 - Collaboration aims to standardize decision-making for frac operations.
The OGInterview: How do Woodside's Growth Projects Fit into its Portfolio?
2024-04-01 - Woodside Energy CEO Meg O'Neill discusses the company's current growth projects across the globe and the impact they will have on the company's future with Hart Energy's Pietro Pitts.