Trans Mountain Corp. plans to begin line fill in March or May on its long-delayed Canadian oil pipeline expansion, depending on the diameter of pipe it uses and assuming no new problems, the Canadian government-owned company said in a filing on Jan. 3.
The company is awaiting a regulatory decision on its request for a construction change.
Line fill is a final step before the expanded Alberta-to-British Columbia pipeline begins service, providing crucial additional access for Canadian oil to refineries on the U.S. West Coast and in Asia.
The project will nearly triple the pipeline's shipments to 890,000 bbl/d.
Trans Mountain said the new schedules assume that it faces no delays caused by challenges drilling into hard rock, such as tool damage. Trans Mountain continues to target the end of the first quarter to begin shipping crude and is developing contingency plans to address any challenges to that schedule, a spokesperson said in an email.
Trans Mountain had asked the Canada Energy Regulator (CER) to allow it to install smaller-diameter pipe in a 1.4-mile (2.3 km) section of the oil pipeline's route after encountering challenging drilling conditions in a mountainous area between Hope and Chilliwack, British Columbia.
The CER denied the request on Dec. 5, later saying that the application did not adequately address concerns about pipeline integrity and the environment. Trans Mountain then asked the regulator to reverse that decision on Dec. 14, warning of a possibly "catastrophic" two-year delay and billions of dollars in losses.
The CER has not yet made a decision.
The pipeline can enter service within one month of mechanical completion, which precedes line fill, Trans Mountain said in the filing.
Canadian heavy oil prices strengthened as the filing suggested Trans Mountain and the regulator are working hard to resolve construction problems, a trader said.
In Trans Mountain's 33-page filing, it told the CER it had considered numerous alternatives before settling on the revised plan for which it is seeking approval.
The company said it has faced growing problems with water flow and abnormal wear on tools as it drills into hard rock.
Under the worst-case scenario for the plan currently approved by CER, the company's horizontal directional drilling approach could fail and require a fresh alternative that may delay the project by two years to 30 months, Trans Mountain said.
Prime Minister Justin Trudeau's Liberal government bought the project in 2018 to ensure the expansion went ahead, but costs have ballooned to CA$30.9 billion (US$23.14 billion), more than four times the original budget.
Recommended Reading
BP Pursues ‘25-by-‘25’ Target to Amp Up LNG Production
2024-02-15 - BP wants to boost its LNG portfolio to 25 mtpa by 2025 under a plan dubbed “25-by-25,” upping its portfolio by 9% compared to 2023, CEO Murray Auchincloss said during the company’s webcast with analysts.
Laredo Oil Subsidiary, Erehwon Enter Into Drilling Agreement with Texakoma
2024-03-14 - The agreement with Lustre Oil and Erehwon Oil & Gas would allow Texakoma to participate in the development of 7,375 net acres of mineral rights in Valley County, Montana.
Bobby Tudor on Capital Access and Oil, Gas Participation in the Energy Transition
2024-04-05 - Bobby Tudor, the founder and CEO of Artemis Energy Partners, says while public companies are generating cash, private equity firms in the upstream business are facing more difficulties raising new funds, in this Hart Energy Exclusive interview.
President: Financial Debt for Mexico's Pemex Totaled $106.8B End of 2023
2024-02-21 - President Andres Manuel Lopez Obrador revealed the debt data in a chart from a presentation on Pemex at a government press conference.
Green Swan Seeks US Financing for Global Decarbonization Projects
2024-02-21 - Green Swan, an investment platform seeking to provide capital to countries signed on to the Paris Agreement, is courting U.S. investors to fund decarbonization projects in countries including Iran and Venezuela, its executives told Hart Energy.