The Canadian government-owned Trans Mountain oil pipeline is no longer profitable after cost over-runs and delays to its expansion project, the country's parliamentary budget officer (PBO) said on June 22.
A report from PBO Yves Giroux said the pipeline has a net present value of negative C$600 million (negative $463.03 million USD), based on the difference between Trans Mountain's cash flows and its C$4.4 billion purchase price.
The report from the PBO, which provides independent advice to Parliament, is a blow to Prime Minister Justin Trudeau, whose government bought the pipeline in 2018 to ensure that the expansion proceeded despite protests. Expansion of other pipelines has since smoothed the flow of crude, one of Canada's most valuable exports.
Trudeau faces criticism that expanding the pipeline is contrary to Canada's goals of cutting greenhouse gas emissions.
Additional delays and increased construction costs would further reduce Trans Mountain's value, the PBO said. If Ottawa cancels the expansion, the government faces a C$14.4 billion write-off, the PBO said.
The cancellation scenario is hypothetical, and the government has no such plans, said a government source. The source added that the PBO analysis of unprofitability does not consider other economic benefits such as jobs.
Trudeau's government has long said it will sell the pipeline once the expansion is nearly complete.
The pipeline moves up to 300,000 bbl/d of oil from near Edmonton, Alberta, to the Pacific coast in British Columbia, and the expansion would nearly triple capacity.
Industry and environmental advocates have starkly different views on the pipeline.
The expansion is critical for Canada's oil industry, ensuring its long-term stability and providing more diverse market access, said Reg Curren, spokesman for producer Cenovus Energy.
The government should cancel the expansion and cut its losses, said Julia Levin, national climate program manager at Environmental Defense, an environmental advocacy group.
"Continuing to throw public dollars at the project would be another broken promise from a government that committed to end fossil fuel subsidies," she said.
The cost of expanding Trans Mountain has jumped to C$21.4 billion from C$12.6 billion, and its in-service date delayed by nine months to late 2023, Trans Mountain Corp. said in February.
Recommended Reading
Triangle Energy, JV Set to Drill in North Perth Basin
2024-04-18 - The Booth-1 prospect is planned to be the first well in the joint venture’s —Triangle Energy, Strike Energy and New Zealand Oil and Gas — upcoming drilling campaign.
TotalEnergies Cements Oman Partnership with Marsa LNG Project
2024-04-22 - Marsa LNG is expected to start production by first quarter 2028 with TotalEnergies holding 80% interest in the project and Oman National Oil Co. holding 20%.
Is Double Eagle IV the Most Coveted PE-backed Permian E&P Left?
2024-04-22 - Double Eagle IV is quietly adding leases and drilling new oil wells in core parts of the Midland Basin. After a historic run of corporate consolidation, is it the most attractive private equity-backed E&P still standing in the Permian Basin?
TotalEnergies to Acquire Remaining 50% of SapuraOMV
2024-04-22 - TotalEnergies is acquiring the remaining 50% interest of upstream gas operator SapuraOMV, bringing the French company's tab to more than $1.4 billion.
EIG’s MidOcean Closes Purchase of 20% Stake in Peru LNG
2024-04-23 - MidOcean Energy’s deal for SK Earthon’s Peru LNG follows a March deal to purchase Tokyo Gas’ LNG interests in Australia.