A U.S. appeals court on April 30 upheld federal approvals for a natural gas pipeline system expansion project in Louisiana and Mississippi, rejecting environmentalists’ claims that the government performed an insufficient review of its climate harms.
A unanimous three-judge panel of the U.S. Circuit Court of Appeals for the D.C. Circuit held that the Federal Energy Regulatory Commission (FERC) was right to determine the Evangeline Pass Expansion project is functionally separate from four related gas infrastructure developments being developed independently. FERC therefore did not need to analyze their emissions together, the D.C. Circuit said.
The Kinder Morgan-backed project would expand existing pipelines to feed more fuel to Venture Global's Plaquemines LNG export terminal in the Gulf of Mexico.
The Sierra Club and Healthy Gulf said in their 2022 lawsuit seeking to vacate FERC's approvals that the expansion and the related projects — new pipeline infrastructure projects that connect to the same export terminal and to the terminal itself — would together cause a massive release of greenhouse gas emissions.
But the D.C. Circuit said on April 30 that since the other projects have separate ownership and would likely be built anyway, FERC was not obligated under federal environmental review laws to consider their collective emissions when issuing approvals.
The environmental groups, Kinder Morgan and FERC didn’t immediately respond to requests for comment.
The projects are all part of a major buildup of LNG export capacity in the Gulf. The U.S. last year became the world’s largest LNG exporter, and that capacity is expected to double before the decade ends.
The environmental groups had argued that FERC violated the National Environmental Policy Act when it segmented its analysis of Evangeline Pass' environmental harms from the other projects.
The groups said the projects are connected because the terminal won’t be able to export gas without supply from the pipelines, and the pipelines wouldn’t have anywhere to put the gas without the terminal.
FERC had argued in court that the cumulative analysis demanded by the environmental groups wasn’t necessary because the individual projects would likely proceed regardless of whether the Evangeline Pass project is approved.
The Evangeline Pass expansion is currently under construction. Work on the Plaquemines terminal is also ongoing and its first exports are expected later this year.
The case is Alabama Municipal Distributors Group v. Federal Energy Regulatory Commission, U.S. Circuit Court of Appeals for the D.C. Circuit, lead case No. 22-1101.
Recommended Reading
What's Affecting Oil Prices This Week? (March 11, 2024)
2024-03-11 - Stratas Advisors expects oil prices to move higher in the middle of the year, but for the upcoming week, there is no impetus for prices to raise.
What's Affecting Oil Prices This Week? (Feb. 26, 2024)
2024-02-26 - Stratas Advisors forecast that global crude production will be essentially unchanged from 2023, which means that demand growth in 2024 will outpace supply growth.
What's Affecting Oil Prices This Week? (May 6, 2024)
2024-05-06 - Stratas Advisors forecast that oil demand for 2024 will increase by 1.41 MMbbl/d in comparison to 2023 and that oil demand will increase by 810,000 bbl/d in comparison to 2Q23.
What's Affecting Oil Prices This Week? (March 4, 2024)
2024-03-04 - For the upcoming week, Stratas Advisors expect the price of Brent will move sideways and will struggle to break through $85.
What's Affecting Oil Prices This Week? (March 25, 2024)
2024-03-25 - On average, Stratas Advisors are forecasting that oil supply will be at a deficit of 840,000 bbl/d in 2024.